How long does it take to build an app?

By Shahid Hussain, senior mobile & web engineer · · Updated

A focused first version of an app usually takes two to four months from agreed scope to the stores. Industry guides put a simple first version at two to four months and an average app at four to six (Topflight), and three to four months is typical for a first version (Netguru). Whole projects run longer: app projects reviewed on Clutch take about 11 months (Clutch). Most of the calendar goes to decisions and waiting, not to writing code, so most of it is in your hands.

The stages, and what sets the length of each

  1. Scope, a few days to two weeks. What the first version does, every screen and its states, the backend and the integrations. A fixed quote comes out of this, and so does the timeline.
  2. Design, if it isn’t done yet. A designer turns the scope into screens. This runs before the build or alongside its first weeks. (More in do you need designs before hiring an app developer.)
  3. The build, weeks to months. Set by the number of screens, the backend and the integrations: payments, maps, chat or AI each add time. One Flutter codebase for iPhone and Android is quicker than two native apps (Flutter or native).
  4. Testing. TestFlight on iPhone, a testing track on Google Play, and fixes for what testers find.
  5. Store review and release. Usually the shortest stage, with one exception below.

Store review, and Google Play’s 14-day test

  • Apple says it reviews at least half of submissions in less than 24 hours, and 90% in less than 48 (Apple). A rejection adds a round trip; the common causes are in why App Store reviews reject apps.
  • Google Play reviews take from a few hours to about a week, and some accounts and apps get longer checks (Google).
  • New personal Google Play accounts (created after November 13, 2023) must run a closed test with at least 12 testers, opted in for the 14 days in a row before you apply for production access (Google). That alone is more than two weeks, so start it as soon as you have a build that works, not the week you planned to launch.

What makes an app late

  • Scope that changes mid-build. Every new screen moves the date, and so does every change to one that’s built.
  • Waiting. For designs, content, API keys, a payment provider’s approval, or store accounts. Apple asks an organization for a D-U-N-S Number to enroll in the Developer Program (Apple), so request it early.
  • Unclear “done”. Without acceptance criteria, the last 10% turns into weeks of small changes.
  • Testing left to the end. Problems found in the last week cost the most time.

How to make it shorter

  1. Launch the smallest version that proves the idea, then add what people ask for.
  2. Bring finished designs with every screen and state.
  3. Open the Apple Developer and Google Play accounts on day one, and start Google Play’s closed test early.
  4. Use one codebase for both platforms unless the app needs native features from the first version.
  5. Agree a fixed scope with written acceptance criteria, so a change is a decision with a date attached, not a surprise.

My timelines

The App Audit takes 5–7 working days, and the Fix & Speed Sprint 2–3 weeks. For the App Build, the timeline is set in the scoped plan, next to the fixed price, before any work starts, and you see progress every weekday. For what each stage costs, see how much it costs to build an app.